TROY, MICH. — Skanska USA Building Inc., in a joint venture with Barton Malow, has been named construction manager and design/builder for the William Beaumont Hospital project located in Troy. The 558,000-square-foot, multi-phased project broke ground in June 2007, with completion slated for October 2010. Harley Ellis Devereaux is providing design services for the hospital. Skanska’s share of the project is 51 percent of the $213 million total cost of construction. The project includes a 223,000-square-foot emergency center and critical care tower. Additionally, the hospital will include a three-story ambulatory care center, a vertical expansion of the West Tower, a loading dock and powerhouse expansion, a 5,400-square-foot MRI addition, and a connector bridge linking the existing main campus to the new ambulatory center on the hospital’s east campus.