GOODYEAR, ARIZ. — Vantage Data Centers has unveiled plans to develop a data center campus, located at the southeast corner of Van Buren Street and Bullard Avenue in Goodyear.
Spanning 50 acres, the center will feature three data center buildings and office space totaling more than 1 million square feet of space. Additionally, the campus will offer a total of 160-megawatts of critical load.
Design, site plan approval and permitting are underway with construction expected to begin in early 2019. The first 32-megawatt data center is anticipated to be online in early 2020.